How to start a coating factory

Six steps between your first message and your first saleable batch. We compress them into 60 to 90 days — and stay on call for 12 months after.

First proposal
3 working days
Signing to first batch
60–90 days
First shipment supports
10–20 t
Technical support
12 months

The sequence

A real order with real dependencies: the formulation is adapted to your local materials before anything ships, and every batch is tested before it is released.

  1. Day 0

    Enquiry and proposal

    Tell us your market, target products, output and budget. We reply within one working day, and within three you have a product range, raw material list, equipment suggestions and prices.

  2. Day 10

    Contract and NDA

    Cooperation agreement and NDA signed. The formulations are licensed to you for the agreed market.

  3. Day 25

    Formulation and samples

    The formulation package and technical documents are handed over. We send samples, or run adaptation trials with the local cement, sand and water you send us.

  4. Day 40

    Raw materials shipped

    The first batch of key materials is loaded with inspection reports and shipped to your port. Standard materials ship 15–20 days after order.

  5. Day 60

    Trial production coaching

    Remote guidance through your first three batches, step by step. Every batch is tested and released only when it meets specification.

  6. Day 90+

    Go to market, supported

    Application manuals, product brochures and test data, plus support for local certification — and 12 months of technical support, renewable after the first year.

What the package includes

  • Waterproof coating formulation

    The recipe, the process, and the numbers behind both

  • Application guides and detailing

    How the product goes on the wall, in pictures and video

  • Coating testing and QC lab

    Data before the formula is final, data before a batch ships

  • Waterproof coating raw materials

    Key materials from China, bulk materials sourced locally

  • Coating plant start-up support

    For 12 months after signing, we run the plant with you

The commercial terms, up front

  • Minimum order

    The first raw material shipment is sized to your trial production plan — usually enough for 10 to 20 tonnes of finished product. After that, order monthly or by batch at stable long-term prices.

  • Payment

    The technical service fee is paid at signing; raw materials are paid per order. T/T accepted, letter of credit negotiable.

  • Confidentiality

    Both sides sign an NDA. The formulations are licensed to you for the agreed market, and we do not compete with you in it — you sell under your own brand.

  • Equipment

    Water-based coatings need a disperser, storage tanks and a filling machine; powder products need a mixer and a bagging machine. We provide the equipment list with parameters and can help with purchasing.

Exact terms are set in the cooperation agreement. Ask and we will send the current standard terms before you commit to anything.

Tell us your market. First proposal within 48 hours.

Send the country, the products you want to make and your planned output. You get a product range, raw material list, equipment suggestions and prices — no obligation.