Plant layout for 200 tonnes a month

Eight hundred square metres, nine people, and a one-directional paint factory layout that keeps raw material, quarantine and finished goods from crossing.

min read
8 min
On this page
Keep the flow one-directional · Size the store, not the mixer · Plan for the power going out

A blending plant is a straight line: material in one end, pallets out the other. Most of the layout mistakes we are called in to fix come from letting that line cross itself.

Keep the flow one-directional

  • Raw material store, weighing, mixing, filling, quarantine, finished goods — in that physical order, on one axis.
  • Untested product must be physically separated from released product, or someone will eventually ship a failed batch.
  • Put the QC lab between filling and quarantine so samples travel metres, not minutes.

Size the store, not the mixer

  • The mixer is rarely the constraint. Raw material storage almost always is, because container quantities arrive all at once.
  • Allow six weeks of raw material at full output, plus space for two weeks of finished goods.
  • Drums need dedicated bunded space with the right fire separation. Retro-fitting it is expensive.

Plan for the power going out

  • Choose a batch size a generator can finish. A high-shear disperser stopped mid-batch on a filled vessel is a serious restart problem.
  • Write the restart procedure before you need it, and train on it.
  • Site the disperser where a vessel can be craned out if it does set — it happens.

The short version

Buy storage before you buy capacity, and never let untested product share a floor with released product.